Determining the load capacity during installation is part of the beam’s calculations. In a standard situation, the PFEIFER-Hybridbeams don’t need to be supported during installation, which is checked by calculation. If a temporary support is required as a result of the calculations, an appropriate recommendation for the assembly company is included in the installation plan or in the installation instructions for the beams. Possible repair of the fire coating (in case of damage during installation) is explained here.